Defects Quantification for a 55ML Waste Water Treatment Plant
On a regional wastewater facility, Accura was engaged to quantify defect claims and assist in preparing supporting submissions. Accura’s forensic quantity surveying capability ensures defect and make-good assessments are grounded in facts.
Level Crossing Removal Alliance - Shutdown Strategy Support
Accura provided delay analysis and shutdown planning support to a major alliance delivering level crossing removals within tightly constrained possession windows.
133MW Wind Farm - Delay and Prolongation Assessment
Accura was engaged by a European EPC contractor delivering a 133MW wind farm comprising 31 wind turbine generators. Our analysis provided a clear cause and effect narrative linking events to programme impact and cost consequence.
Commercial and Subcontract Support for a South Australia Substation Upgrade
Accura’s advisory services draw on deep experience in power infrastructure, enabling us to provide disciplined, contractually sound commercial advice for a substation upgrade project in South Australia.
Growth Area Station Program | Delay Assessment
Accura Consulting undertook delay analysis for a new station development with our delay experts exposing the factual and logical basis of the alleged delay events, addressing concurrency and mitigation in detail.
Gas Turbine Project | Delay Expert Appointment
Accura Consulting’s delay experts were engaged as delay expert in adjudication proceedings concerning a gas turbine project where a subcontractor alleged critical delay.
Gas Plant Upgrade in Regional Victoria
Accura Consulting was engaged by a specialist EPC contractor to provide quantum and delay expert services on a technically challenging gas plant upgrade project in regional Australia.
Complex Major Central Sydney Precinct Development
Our team was brought in to assist with claims consulting, and to provide quantum and delay expert services relating to variations, interface issues, and cumulative delay impacts.
Claims Support for Royal Hobart Hospital Redevelopment
Accura Consulting was appointed by a tier one contractor to provide commercial and claims advisory services on the Royal Hobart Hospital Redevelopment.
Stadium Roof Issues – Quantum Expert Advisory
Accura Consulting was engaged by a specialist subcontractor involved in the construction of a major stadium in Western Australia to provide quantum expert services.
Delay, Disruption and Claims Management for Major Road Piling Works
Accura Consulting was engaged by a major civil works contractor to provide delay, disruption, and claims management services during the delivery of piling works on the Pacific Highway Upgrade
Renewables Challenges on Bulgana Wind Farm Project
Accura Consulting was appointed to support a leading international EPC contractor during the construction of the Bulgana Wind Farm, a 194MW renewable energy project located in western Victoria.
WestConnex M4 Project Delays and Unforeseen Site Conditions
Accura Consulting was engaged by a major joint venture contractor to provide commercial and claims advisory services during the delivery of the WestConnex M4 East—a key stage of one of Australia’s largest transport infrastructure projects.
Claims and Quantum Advisory for Sydney Metro City and Southwest Project
Accura Consulting was engaged by a tier one contractor to support the delivery of the radio communications package on the Sydney Metro City & Southwest project.
Claims and Quantum Advisory for a Major Australian LNG Project
Accura Consulting was engaged by a tier one international contractor to provide claims and quantum advisory services on a major liquefied natural gas (LNG) development located in Northern Australia.
Mixed-use commercial building refurbishment hit delay
Accura Consulting was appointed as the delay and disruption expert for the refurbishment of a prominent mixed-use commercial building located in Melbourne’s CBD.
Southern Queensland Correctional Facility Project
An important correctional facility construction project in Southern Queensland required claims, quantum, and delay advisory support.
Rail and Tunnel Infrastructure Project runs into delays and disruption
A significant rail and tunnel construction project faced severe disruption due to the COVID-19 pandemic.
Wind Farm in New Zealand | Snapshot
Accura Consulting experts provide clients with a tailored approach to their problems, relying on a fact-based approach to analyse delays with impartiality.
Victorian Solar Farm Project
One of the challenges found in many renewables projects relates to connections and grid issues. For one major wind project in Victoria, this was the case for the EPC.