On a regional wastewater facility, Accura was engaged to quantify defect claims and assist in preparing supporting submissions.
We reviewed as-built documentation, commissioning records and defect notices to establish scope and responsibility. Quantities were verified against drawings and site records, and remediation rates were benchmarked against market data to ensure reasonableness.
Location: Australia
Service: Quantum Expert, Forensic Quantity Surveying, Delay Expert, Claims Consulting
Industry: Water
Accura expert:Paul McArd
The assessment extended beyond simple valuation. We examined causation, allocation of risk under the contract and the impact of rectification works on programme and site overheads.
Accura’s forensic quantity surveying capability ensures defect and make-good assessments are grounded in measured quantities, contractual interpretation and commercial realism.
This project has been anonymised out of respect for the client.