Proving delay costs: how preliminaries fit into a contractor’s claim

Construction workers on site beside an excavator and concrete truck, showing the labour and plant costs that can grow when a project is delayed

A contractor will usually claim delay costs when an employer-risk event makes the work take longer and causes additional cost.

The contractor must show that:

  • the work took longer than it would have without the delay; and

  • the delay caused costs that would not otherwise have been incurred.

Delay claims are usually valued by reference to actual cost: loss and/or expense under the contract, or damages at common law. The contract may instead provide agreed delay rates, reasonable rates or valuation under its variation provisions, including a schedule of rates.

This article focuses on claims based on actual loss and expense.

Most construction contracts provide an express remedy for events that might otherwise support a damages claim. Clear wording is needed to exclude common law damages, and contractual rights will generally sit alongside common law remedies.

Damages put the affected party in the position it would have been had it not been for the breach. They cannot place that party in a better position. Recovery is also limited where the loss is too remote.

Mitigation

A contractor must take reasonable steps to reduce its loss, but it need not do more than is reasonable. It cannot recover loss that it could reasonably have avoided. The reasonable cost of mitigation may itself be recoverable. The employer bears the burden of proving a failure to mitigate but the contractor should keep evidence of the steps it took.

Critical and non-critical delay

Recoverable delay costs can arise from both critical and non-critical delay.

Standard form contracts commonly allow an extension of time and financial relief where an employer-risk event delays completion. Some events, such as force majeure, may give time but no money, depending on the contract.

Non-critical delay does not move the completion date, so it will not usually support an extension of time. It may still increase the cost of an activity by keeping labour, plant or supervision engaged for longer. If the contract does not provide payment for that loss, the contractor may need to claim damages at common law.

The contract may nevertheless allow recovery for non-critical delay. In CMC v WICET, CMC recovered loss caused by directions that delayed a non-critical activity because those directions were valued as variations.

Main heads of delay cost

The main heads of a delay claim may include:

  1. labour;

  2. preliminaries (on-site overheads or indirect project costs);

  3. subcontractor claims;

  4. head office overheads;

  5. loss of profit;

  6. resource cost increases and inflation; and

  7. finance charges and interest.

Whether the claim is made under the contract or at common law, the contractor can generally recover only the additional loss or cost it proves it has suffered. It must establish that loss on the balance of probabilities.

How preliminaries fit into delay costs

Preliminaries, also called project-specific or on-site overheads, are costs needed to deliver the project but not incorporated into the completed work. Some are fixed, one-off costs, such as site establishment and demobilisation, and are not increased simply because the project is delayed.

Other preliminaries are time related. Examples include site staff, site accommodation, utilities, security, and plant or equipment used to support the work.

When delay keeps those resources on the project for longer, the resulting additional cost may form part of the delay claim. The amount depends on which resources were extended, for how long, and why they remained necessary.

Preliminaries should be distinguished from head office overheads. However, the boundary is not always clear. Work performed at head office may still be a project preliminary cost if it was carried out for that project. Correct classification matters, particularly where the contract applies a percentage for head office overheads to delayed preliminaries.

A practical test is whether the cost would have been incurred even without the project. If so, it is likely a head office overhead; if the resource or service was needed specifically for the project, it is more likely a preliminaries cost.

A head office resource can therefore be a general overhead, a direct project cost, or a mixture of both. The classification should follow the work performed and the available records.

Valuing delayed preliminaries at cost

Where delayed preliminaries are claimed as loss and/or expense or common law damages, the usual starting point is the reasonable actual cost caused by the delay. The contractor should support that cost with its accounting records and other project evidence.

Evidence may include purchase orders, invoices, payroll records, journals, bank statements, ledgers and final account records. For hired resources, the relevant cost may be the additional hire charge. For contractor-owned resources, the valuation may instead involve lost hire opportunity, financing cost, maintenance or depreciation, depending on the loss suffered.

The mix of time-related preliminaries varies by project. On a large project, site staff, labour, plant and equipment may be the main items. For site staff, the claim should identify each person's role and show how their work related to the delay.

A fully additional resource used only during the delay should be straightforward to identify. Where a resource was only partly used for delay-related work, timesheets and activity records must separate the recoverable time from normal project work.

Site staff can be the largest part of a delayed preliminaries claim. Payroll information is sensitive and may require an agreed verification process, such as review by an independent accountant or expert rather than unrestricted disclosure to the other party.

The same approach applies to staff working across locations or projects. Off-site staff performing project-specific work, and site-based staff supporting several projects, should record their time clearly so that only the relevant share is claimed.

Plant and equipment may be idle or underused during a delay. If hired, the additional hire charges may be recoverable. Different evidence is needed for contractor-owned plant.

For contractor-owned plant, a contractor claiming lost hire income must show that a genuine hire opportunity was lost because of the delay. If it cannot, the claim may instead be based on proven financing costs, maintenance, tied-up capital or depreciation.

The contractor must prove that each cost was reasonably incurred, caused by the relevant delay, and kept to a reasonable minimum.

For lawyers and commercial managers, the approach is consistent: establish the contractual basis for entitlement, link the delay event to the resources it extended, and present the cost evidence clearly, logically and in a form that can be audited.

Records and proof

The contractor should identify the labour, plant, preliminaries and administration costs linked to the delayed activities, then reconcile those costs to the amount claimed.

Its cost system should record not only what was spent, but why the cost was incurred and how it relates to the delay event.

Modern construction accounting systems can provide this detail if costs are coded correctly. A cost ledger alone is not enough: the records must explain causation and support the recoverable amount.

Head office, administration and support costs caused by an instruction or breach should be separated from normal business costs and from costs caused by the contractor's own performance. Without that separation, entitlement and quantum will be difficult to prove.

“A cost ledger alone is not enough: the records must explain causation and support the recoverable amount.”
— Andrew McKenna, Accura Consulting

The valuation method always depends on the contract and, where the contract does not deal with the issue, the governing law. Preliminaries are a key part of this analysis because delay often extends time-related site costs.



At Accura Consulting, our team of experts work with clients to create a tailored solution to problems. If you have an issue and want expert support, get in touch.


 
 

Related News and
Insights from Accura

Andrew McKenna

Andrew is Accura Consulting’s Director of Delay and Planning. He has provided oral and written testimony in formal proceedings as a delay expert witness in Australia and overseas. Key to Andrew’s ability to help design a tailored approach to resolving problems is his logical and common-sense approach, breaking down complexity to ensure understanding and acquiescence from all parties.

Next
Next

Ninety days late: proving the costs attributed to delay