Many wind projects engage an EPC to lead the manufacturing, design, development, engineering and procurement of a project. Due to legislation, environmental factors, and shortage of skilled labour, projects often experience delays.
Accura Consulting was engaged by a Major wind EPC and turbine manufacturer that had received several claims for variations and EoTs from subcontractors. Costs claimed where excessive and the time claimed purported all the culpability to the EPC.
Location: Australia
Service: Claims Consulting, Forensic Delay Analysis, Forensic Quantity Surveying
Industry: Renewables
Accura expert: Paul McArd
Accura Consulting are experts in renewables projects and are able to use hands-on experience to work quickly and effectively to find solutions to problems.
Accura Consulting experts forensically reviewed the contract, scope and specification and provided a robust contractual and factually based rebuttal.
The team also undertook a forensic quantum analysis to correctly value the costs claimed as independent experts which provided a powerful and persuasive case which ultimately encouraged a settlement.
A delay analysis was undertaken which demonstrated significant concurrent delays which highlighted the EPC’s rights to liquated damages.
All claims where successfully settled based on factual evidence, saving the EPC significant costs and providing them confidence to progress their project.
*out of respect for our clients’ privacy, we have opted to omit names from this case study.
Back to Experience