News and Insights
Never miss an update
Sign up with your email address to receive news and updates.
Video Insights
Explore our video series featuring quantum expert, delay expert, and claims insights to help you understand your position and how Accura Consulting can support you find a construction dispute resolution to your problem.
Featured Video
Featured
All articles
Claims Timelines and What Makes Them So Important
Maintaining a detailed timeline of events will support an extension of time and cost claim. Here are the main reasons why a timeline is important.
Royal Institution of Chartered Surveyors Dispute Resolution Team of the Year
Accura Consulting is the winner of the RICS Dispute Resolution Team of the Year for 2022.
Top Issues Faced by Tunnelling Projects
Tunnelling projects are complicated, and all parties — the customer, EPC contractors and subcontractors — expect the work to be done on-time and on budget but delays and cost overruns happen.
Delay Analysis Under the NEC Contract
The NEC contract prescribes that an extension of time, delay and quantum be determined prospectively. The NEC contract requires the contractor to maintain an up-to-date program.
Pricing of Construction Work when Providing an Independent Quantum Assessment
Whether it be assessing insurance claims, variation claims, or the remediation of defective works, a quantum expert is called upon to provide an independent subjective opinion to assist an insurer or a tribunal or, in some cases, to help parties settle a matter outside of formal proceedings.
The Contract Program and Demonstrating Delay
The term “Contract Program” is often used in reference to the Construction or Contractor’s Program. The Construction (or Contractor’s) Program is basically the execution plan and timeline of how the works under the Contract will be carried out and measured. It should consider the key sequences of work and resource dependencies. It should also, depending on the Contract, identify the critical path and the relationships between the planned activities and interfaces.
What Type of Delay Analysis is Required Under the Contract?
This article considers the contractual requirements regarding the most appropriate and accepted method of delay analysis in the commonly used Australian Standard General Conditions of Contract.
Four Delay Analysis Methodologies You Need to Know
A lot has already been written about various delay analysis methodologies. The purpose of this article is to summarise the pros and cons of the most commonly accepted methodologies and highlight where they might best be used.
Mitigation, Acceleration and Constructive Acceleration
In this article we are going to consider the differences between mitigation, acceleration, and constructive acceleration. The recent case of V601 v Probuild[1] is of interest, as it demonstrates that a constructive acceleration claim can be successful in certain circumstances.
The Importance of Contemporaneous Records
Project teams are often told to keep daily or even hourly records of events that occur on-site if a claim for additional time and cost arises. These records are known as contemporaneous records in that they are ‘recorded’ when the event occurs.
Who owns the float?
A common question when demonstrating entitlement to an Extension of Time is, who owns the float?
When considering who owns the float, one first must understand the various definitions of 'float' typically associated with construction projects. Secondly, one must understand the applicable contractual clause relating to claiming an extension of time.
10 Crucial Questions To Ask A Delay Expert
An independent delay expert needs to be impartial when engaged in providing early delay and planning advice, so clients understand their actual liabilities or opportunities.
Prolongation Costs – A Non Global Approach
Prolongation or delay costs must reflect the actual losses incurred by a claimant unless otherwise stated in the contract.
More often than not, claimants derive prolongation costs by determining an average daily rate taken from the preliminaries and/or indirect costs listed in the contract and multiplying that rate by the number of days delay.
How to Use Quantum and Delay Experts to Avoid Global Claims
In this on demand presentation Andrew McKenna and Paul McArd discuss what a global claim is and how they can be avoided by using quantum and delay experts.
Delay Analysis – A Common Sense Approach
Delay analysis is not the “dark art” it is often perceived to be. It is simply how to prove the purported delaying events impact (the cause) on time (the effect). The analysis must provide a clear and succinct distinction of the chain of events that have hindered progress and ultimately caused the delay(s) to completion.
10 Crucial Questions to ask a Quantum Expert
An independent quantum expert needs to be impartial when engaged in providing early quantum advice, so clients understand their actual liabilities or opportunities.
Digging Deeper and Untangling Quantum and Delay Claims
When drafting a quantum and/or delay claim based on several events, claimants commonly use inference rather than causation to build their arguments. This approach is sometimes used by claimants as they tend to focus on the monetary amounts lost and/or the delays they have incurred, rather than identifying causation.
Never miss an update
Sign up with your email address to receive news and updates.
Accura Consulting is purposefully lean and independently owned.
We are forensic quantum and delay experts not bound by restrictions and bureaucracy, enabling us to easily adapt to rapidly changing landscapes and provide a tailored approach effective to the situation.
We are committed to establishing and nurturing long-term client relationships built on respect, trust and excellence.
Our Vision is to help our clients make confident decisions. We are there to provide guidance and help clients gain a better understanding of the process and situations they find themselves in. That’s why our news and insights features an array of learning articles to help you find the answers to problems you may encounter.