
News and Insights
Video Insights
Explore our video series featuring quantum expert, delay expert, and claims insights to help you understand your position and how Accura Consulting can support you find a construction dispute resolution to your problem.
Featured Video
Featured
All articles
As-Planned vs As-Built Delay Analysis
A simplistic, retrospective methodology, which in its simplest form compares the as-built program to the planned (baseline) program.
How Can Flora and Fauna Cause Delays?
Infrastructure, residential, and commercial construction projects can potentially impact natural habitats, affecting flora and fauna.
Delay Analysis Under the NEC Contract
The NEC contract prescribes that an extension of time, delay and quantum be determined prospectively. The NEC contract requires the contractor to maintain an up-to-date program.
The Contract Program and Demonstrating Delay
The term “Contract Program” is often used in reference to the Construction or Contractor’s Program. The Construction (or Contractor’s) Program is basically the execution plan and timeline of how the works under the Contract will be carried out and measured. It should consider the key sequences of work and resource dependencies. It should also, depending on the Contract, identify the critical path and the relationships between the planned activities and interfaces.
What Type of Delay Analysis is Required Under the Contract?
This article considers the contractual requirements regarding the most appropriate and accepted method of delay analysis in the commonly used Australian Standard General Conditions of Contract.
Four Delay Analysis Methodologies You Need to Know
A lot has already been written about various delay analysis methodologies. The purpose of this article is to summarise the pros and cons of the most commonly accepted methodologies and highlight where they might best be used.
Mitigation, Acceleration and Constructive Acceleration
In this article we are going to consider the differences between mitigation, acceleration, and constructive acceleration. The recent case of V601 v Probuild[1] is of interest, as it demonstrates that a constructive acceleration claim can be successful in certain circumstances.
Who owns the float?
A common question when demonstrating entitlement to an Extension of Time is, who owns the float?
When considering who owns the float, one first must understand the various definitions of 'float' typically associated with construction projects. Secondly, one must understand the applicable contractual clause relating to claiming an extension of time.
10 Crucial Questions To Ask A Delay Expert
An independent delay expert needs to be impartial when engaged in providing early delay and planning advice, so clients understand their actual liabilities or opportunities.
Delay Analysis – A Common Sense Approach
Delay analysis is not the “dark art” it is often perceived to be. It is simply how to prove the purported delaying events impact (the cause) on time (the effect). The analysis must provide a clear and succinct distinction of the chain of events that have hindered progress and ultimately caused the delay(s) to completion.
Digging Deeper and Untangling Quantum and Delay Claims
When drafting a quantum and/or delay claim based on several events, claimants commonly use inference rather than causation to build their arguments. This approach is sometimes used by claimants as they tend to focus on the monetary amounts lost and/or the delays they have incurred, rather than identifying causation.
Never miss an update
Sign up with your email address to receive news and updates.
Accura Consulting is purposefully lean and independently owned.
We are forensic quantum and delay experts not bound by restrictions and bureaucracy, enabling us to easily adapt to rapidly changing landscapes and provide a tailored approach effective to the situation.
We are committed to establishing and nurturing long-term client relationships built on respect, trust and excellence.
Our Vision is to help our clients make confident decisions. We are there to provide guidance and help clients gain a better understanding of the process and situations they find themselves in. That’s why our news and insights features an array of learning articles to help you find the answers to problems you may encounter.