Case Summary:  Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd 

delay expert delay analysis prebuilt

Probuild Constructions (Aust) Pty Ltd was the head contractor on the refurbishment of the Tank Stream Hotel in Sydney and subcontracted DDI Group Pty Ltd under an amended AS 4303 subcontract. 

The subcontract: 

  • Set a Date for Practical Completion 

  • Contained a standard extension of time (EOT) regime 

  • Also gave Probuild a discretionary power to grant an EOT even if DDI had not made a compliant or timely EOT claim 

After the Date for Practical Completion had passed, Probuild: 

  • Directed substantial variations 

  • Allowed the works to continue 

  • Later sought to set off liquidated damages against DDI’s payment claim, on the basis that no EOT had been formally granted 

DDI claimed payment under the Building and Construction Industry Security of Payment Act 1999 (NSW), arguing that Probuild could not rely on LDs for delay it had caused. 

Adjudication and appeal 

The adjudicator rejected Probuild’s LD set‑off, effectively applying the prevention principle (a party cannot insist on strict contractual time obligations where it has itself caused delay). 

Probuild challenged the determination, arguing: 

  • The adjudicator denied procedural fairness 

  • The prevention principle had not been expressly argued by either party. 

The NSW Court of Appeal dismissed the appeal. 

Key findings 

The Court held that: 

Prevention principle applies: A head contractor cannot levy liquidated damages for delay it has caused, including delay arising from variations instructed after the contractual completion date. 

Discretionary EOT powers must be exercised: Where a contract gives a discretionary power to extend time, that power cannot be ignored to manufacture entitlement to LDs. 

Implied duty of good faith: The discretion to grant EOTs was constrained by an implied duty of honesty and good faith, requiring Probuild to fairly recognise delay it caused. 

No denial of procedural fairness: The adjudicator was entitled to apply legal principles arising naturally from the facts, even if not labelled by the parties. 

Why this case matters  

This decision is a warning case for head contractors and principals who: 

  • Instruct variations late 

  • Let projects drift past completion 

  • And then attempt to recover liquidated damages on technical notice failures 

It confirms that commercial reality will prevail over strict formality where a party’s own conduct causes delay.  

Lessons Learned 

1. Principal‑caused delay still matters, even if notices are late 

Even though DDI failed to comply strictly with notice requirements, the Court accepted that Probuild knew about the delay it was causing through variations and revised construction programs. 

Key Takeaway 

  • Late or imperfect EOT notices weaken your position, but they do not automatically defeat it. 

2. Liquidated damages cannot coexist with prevention 

A principal or head-contractor cannot: 

  • Direct late changes 

  • Consume float 

  • Push work beyond the Date for Completion and then claim liquidated damages for the same period  

Key Takeaways 
If you are instructed to keep working past completion, carefully document: 

  • Variation instructions 

  • Program impacts 

  • Site directions 

These facts support a prevention argument even in fast‑track disputes. 

3. Discretionary EOT clauses are not “optional” 

Many contracts allow a superintendent or head-contractor to grant EOTs “at their discretion”. Probuild v DDI confirms that this discretion must be exercised honestly and fairly, not strategically. 

Key Takeaways 
If the contract allows discretionary EOTs: 

  • Demand they be exercised 

  • Point to the prevention principle 

  • Escalate early if discretion is being used oppressively 

4. “Good Faith” 

The Court grounded its reasoning not just in prevention, but in an implied duty of good faith constraining how time powers are exercised. 

Key Takeaways  
Where a principal’s conduct appears tactical or opportunistic, good faith arguments can strengthen: 

  • EOT claims 

  • Defences to LDs 

  • Security of payment adjudications 

5. Security of payment is a powerful equaliser 

The case arose in an adjudication context. The Court reinforced that adjudicators can apply well established legal principles. 

Takeaway for contractors 
In payment disputes: 

  • Focus on facts and conduct, not just clauses 

  • Prevention arguments are highly effective in adjudication 

  • Do not assume technical non‑compliance is fatal 

Summary Actions for Contractors 

  • Record all late variations and directions 

  • Track delay causation in programs 

  • Issue EOT notices where possible, and don’t panic if they are late 

  • Challenge LDs where principal conduct causes delay 

  • Use prevention and good faith arguments in adjudication 



At Accura Consulting, our team of experts work with clients to create a tailored solution to problems. If you have an issue and want expert support, get in touch.

 
 

Related News and
Insights from Accura

Andrew McKenna

Andrew is Accura Consulting’s Director of Delay and Planning. He has provided oral and written testimony in formal proceedings as a delay expert witness in Australia and overseas. Key to Andrew’s ability to help design a tailored approach to resolving problems is his logical and common-sense approach, breaking down complexity to ensure understanding and acquiescence from all parties.