Why Courts Expect a Logical and Factual Delay Analysis
When delay claims reach court, one question dominates: what truly caused the delay, and can it be proved? In V601 Developments v Probuild, Justice Digby set the benchmark.
Delay analysis under scrutiny: Santos v Fluor [2025] QSC 184
Santos v Fluor confirms that delay analysis is not an abstract exercise in software or spreadsheets. Delay Expert, Andrew McKenna explains how it is a forensic exercise rooted in evidence, requiring professional judgment, and clear reasoning.
When Delay Methods Fail the Facts - White Constructions Pty Ltd v PBS Holdings Pty Ltd
Delay methodologies don’t always survive the evidence test. This case had as planned versus as built windows approach and a collapsed as built, or but for, analysis.
Exploring the Dynamic As-Built Program of Delay Analysis
The dynamic critical path method makes demonstrating delay after the fact much easier. It negates the need to reconstruct the as-built programme so that a clear critical path can be demonstrated to prove Extension of Time entitlement.
Mega Project Cost Blowouts and How the Fixed Price, Lump Sum Contract Doesn’t Help
Recent Australian mega-projects have experienced significant cost overruns due to unsuitable procurement methods, particularly fixed-price lump sum contracts that fail to accommodate project complexities and risks.
Retrospective Delay Analysis: Still Cause and Effect, Even When You Start With the Effect
There’s been a quiet shift in how some delay practitioners interpret “cause and effect” analysis, and not always for the better.
Delay Expert Review: Time Impact Analysis vs. As-Planned vs. As-Built
Choosing the right methodology for forensic delay analysis is critical to accurately evaluating project delays and resolving disputes.
Why Do Mega Projects Continue to Experience Cost Blowouts?
Recent Australian mega-projects have experienced significant cost overruns due to unsuitable procurement methods, particularly fixed-price lump sum contracts that fail to accommodate project complexities and risks.
The Role of Records and Evidence in Forensic Delay Analysis
Delay expert, Andrew McKenna explores why records are crucial and what types of evidence are most effective to support delay analysis.
Key Challenges in Analysing Construction Delays
Delay expert, Andrew McKenna highlights the key hurdles faced by delay experts and planning experts in analysing construction delays, alongside practical lessons to overcome these issues.
Addressing Baseline Programme Integrity in Delay Analysis
Delay expert, Andrew McKenna discusses the importance of baseline programme integrity, common challenges, and strategies for maintaining robust baseline programmes in Australian construction projects.
The Pros and Cons of As-Built But For Analysis - a Delay Expert Guide
One of the most valuable methods of delay analysis is As-Built But For, also known as the Collapsed As-Built method. Delay Expert, Andrew McKenna details the pros and cons of the method.
What is concurrent delay? A Delay Expert’s explanation
Concurrent delay in extension of time claims occurs when multiple delay events happen simultaneously or overlap on a construction project, impacting the critical path. They can be complex and the services of a Delay Expert can prove effective.
What Does Negative Float Really Represent?
While the term "negative float" has become standard in scheduling jargon, it is a misnomer that oversimplifies a complex issue.
Key Issues Faced by Hospital Construction Projects
As populations grow, the demand for quality healthcare facilities becomes increasingly urgent. Hospitals must be designed and constructed to serve the public for years to come, with the flexibility to adapt to emerging healthcare needs.
The Pros and Cons of Time Impact Analysis - a Delay Expert Guide
When reviewing which type of delay analysis is most important for a specific case, it’s worth considering the pros and cons of the most commonly accepted methodologies. One of the most popularly used methods is time impact analysis.
The Pros and Cons of Impacted As-Planned Analysis - a Delay Expert Guide
Impacted As-Planned is a prospective methodology that relies on impacting the originally planned sequence of works with the delay event.
Case Study Lessons from Zweite M/S “Philippa Schulte” Shipping GmbH v PSA Corp Ltd for Delay Experts
The Zweite M/S “Philippa Schulte” Shipping GmbH v PSA Corp Ltd [2012] SGHC 135 case highlights essential lessons for Delay Experts and Quantity Surveyors.
Balancing Costs and Delay Recovery with Mitigation and Acceleration
Delays are a common challenge in construction projects, often leading to disputes, financial losses, and strained relationships between stakeholders.
How to Avoid Delays in Complex Construction Projects
Managing delays in complex projects requires a proactive approach, robust planning, and effective communication.
Never miss an update
Sign up with your email address to receive news and updates.
Accura Consulting is purposefully lean and independently owned.
We are forensic quantum and delay experts not bound by restrictions and bureaucracy, enabling us to easily adapt to rapidly changing landscapes and provide a tailored approach effective to the situation.
We are committed to establishing and nurturing long-term client relationships built on respect, trust and excellence.
Our Vision is to help our clients make confident decisions. We are there to provide guidance and help clients gain a better understanding of the process and situations they find themselves in. That’s why our news and insights features an array of learning articles to help you find the answers to problems you may encounter.