A large mining owner and operator required a contractor to conduct underground mining services at one of its sites in South Australia.
Procuring new contractors can be a complex process and often requires a tailored solution. The mining owner and operator required support to procure a new underground mining services contractor under a specific relationship/alliancing-type agreement.
Featured project value: x
Project Date: x
Location: Australia
Service: Commercial and Contract Management
Industry: Oil and Gas
Accura expert: Paul McArd
Accura Consulting deployed its commercial and contract management expertise to support the mining owner and operator prepare contract schedules including Alliance Charter to guide behaviours for the contract.
Working closely with the client, our team also conducted a review of the cost model to determine value for money in the cost reimbursable model.
A key part of developing a relationship/alliancing-type agreement was the creation of a pain-gain share mechanism to facilitate appropriate balance for risk and reward for all parties to the contract.
Preparing and reviewing the contract required an attention to detail and ability to negotiate clearly and effectively with other parties on key contractual clauses, gaining agreement on departures.
*out of respect for our clients’ privacy, we have opted to omit names from this case study.
Back to Experience