• 18/6/25

Delay Analysis Under the NEC Contract

The analysis of compensable events and extensions of time can be determined either prospectively or retrospectively. For the most part, the analysis of delay and quantum is best determined retrospectively.  

The NEC contract, however, is different. The NEC contract prescribes that an extension of time, delay and quantum be determined prospectively.   

The NEC Engineering and Construction Contract promotes a “best for project” approach to collaborative contracting by “acting in a spirit of mutual trust and co-operation”. The contract requirements with regard to change management and, more specifically program, require the contractor to maintain an up-to-date program.  

What type of prospective analysis should be used?

The NEC contract prescribes a prospective form of delay analysis methodology, known as a “time impact analysis”. A prospective or “cause-and-effect” analysis models the likely impact of the delaying event at the approximate time the delay occurred, whereas a retrospective or “effect-and-cause” analysis demonstrates the impact of the delay impact in hindsight. 

A prospective analysis is suitable when the project delivery is ongoing, and in the essence of the NEC contract, promotes the early assessment of an entitlement to an Extension of Time at the proximate time the delay event occurred. This prevents the “wait-and-see” approach often taken by the Employer.  

The contract has been criticised for its lack of specific provisions for post-completion delay analysis i.e., retrospectively. However, if a provision for a retrospective analysis was made, it would permit the Employer to adopt a “wait-and-see” approach.  

Prospective Analysis in action

In Fluor v Shanghai Zhenhua Heavy Industry [2018], Sir Anthony-Edwards Stuart considered the prospective analysis of two expert reports. Both were rejected as he held that a prospective analysis is suitable for an extension of time, whereas a retrospective analysis is suitable when there are numerous competing factors.  

Similarly, the NEC contract prescribes that associated costs follow the prospective approach i.e., the likely cost at the time of the compensable event, as opposed to the actual cost incurred (retrospectively).  

On valuing a change to price, Sir Anthony-Edwards Stuart said:  

“There has been an extensive debate about the correct approach to delay analysis. Mr Morgan said, and I would accept, that a prospective analysis – in other words considering the critical path at any particular point in time as viewed by those on the ground at that time – does not necessarily produce the same answer as an analysis carried out retrospectively. The former is the correct approach when considering matters such as the award of an extension of time, but that is not the exercise with which the court is concerned in this case. I agree that some form of retrospective analysis is required”.

The determination of a change to price should be made retrospectively in the way that damages are, ergo the actual cost incurred.  

Key Takeaways

  • Regular, contemporaneously updated programs are vital  

  • Time and cost impact of a compensable event must be determined at the time of the event 

  • However, this does not preclude the impact from being assessed after the fact in case of a dispute  

At Accura Consulting, our team of experts work with clients to create a tailored solution to problems.

To find out how we can help, get in touch.

Previous

Q&A: Key Roles in Construction Disputes

Next

The Importance of Contemporaneous Records