Construction Planners and contract managers reviewing a site plan

The words planning and programming are often used interchangeably to describe two distinct functions of project management. Planning constitutes how the project will be executed (the plan), whilst programming concerns the communication of the plan.  

Planning starts at the time of tender and continues through to completion. The plan constantly evolves as the project progresses, as should the program.  

The program consists of a sequence of logic-linked activities in line with the project plan of varying duration from commencement to completion, typically in the form of a Bar (Gannt) Chart. A good plan is constantly updated to reflect change and progress. A planner manages this process and its communication through the program. However, to successfully execute the plan, the project must “own” the program.  

“If you fail to plan, you are planning to fail!”
— Benjamin Franklin

The Critical Path

The project critical path is usually determined through programming software using the critical path method (CPM). Simplistically, the critical path identifies the most time (or resource) sensitive sequence or “path” of activities through the program from start to finish. The CPM is also widely accepted as the preferred method of demonstrating the causation and effect of delaying events. 

Common Pitfalls

The baseline master program or “contract” program is a static document 

Whether it be due to a delaying event, subsequent mitigation strategy, or work not captured in an earlier revision, for a program to be a useful project management tool it must be updated to reflect any significant deviation from the originally intended plan. Otherwise, the program will become irrelevant.  

No matter how robust and detailed the original plan is, it will invariably change throughout the course of a project. An accompanying (basis of schedule) document which substantiates and justifies the changes must be submitted with the revised baseline, and its approval sought from the clients representative or otherwise.  

The program is solely used for the purpose of monthly reporting  

It is often a requirement that projects status be reported against the baseline or “contract program” to demonstrate progress. The planner or program operative often only considers the works planned to have been undertaken in the previous nominal time frame (typically a month) between reporting periods. Activity commencement and completion dates or a perceived percentage complete of activities in progress are simply input, overriding the planned logic. The activities after the update are rescheduled in accordance with the preceding activities’ anticipated completion date based on a software algorithm. This is “programming”, not planning.  

Program Updates 

The planner or program operative should instead update the program contemporaneously by modifying the as-planned logic and activity durations to reflect what occurred more frequently than the nominal reporting period. Additional activities (or “fragnets”) should be added where necessary to rationalise a change to activity duration. Similarly, future activity logic and durations should be reviewed and any changes noted in the basis of schedule document, and be accompanied by substantiating records. This way, a “live” (as in it has a historical critical path) as-built program is maintained and a more robust forecast is communicated.  

Multiple programs  

A project should have a single master program that incorporates the intent of the entire construction process from commencement to completion in an appropriate level of detail. Short-term (look-a-head), detailed programs should be developed by the respective contributor. However, their content must relate directly to the master program, which is managed solely by the planner or program operative.  

 Managing and controlling multiple programs is difficult and time consuming. Often contractors see it as prudent to have two master programs: A “contract” program for reporting and a “target” program to actually work to. This approach is fraught with trouble since the project will have a different status for each program for the same works in the same respective period. Therefore, making it difficult to prove causation in the event of delay and for the party privy only to the “contract” program to understand their key interfaces and deliverables. 

 Planning and programming are not the same. The program is the “vehicle” by which to communicate and update the plan. It should not be seen as just a contractual obligation, but an essential tool in the management of projects.  

Key Issues in Planning and Programming

The baseline level of detail  

All too often, baseline programs contain either too much or too little detail. An overly complex baseline can be challenging to manage and can quickly become irrelevant if it is not regularly updated. The level of detail must be proportional to the complexity of the project. However, sub-programs or short-term programs should be developed, which relate directly to the baseline or “master” program.  

The tender program is often used as the basis for the baseline program. It should be a fully logic linked network of activities that captures the true critical path and general delivery methodology, including the project key interfaces, deliverables and constraints. In addition, one must consider the contractual obligations concerning the program. For example, some of the Australian standard forms of contract deem that the tender program is the baseline program (AS2124) or is deemed a contract document, as is the case of AS4000.  

Upon contract award, the contractor is usually required to submit a baseline or “contractors” program within a relatively short time frame (sometimes referred to as the “contract” or “construction” program). This updated program should capture more detail in the initial phases of the project, say the first six months, depending on its complexity and duration. Notwithstanding the contractual obligations regarding the program, the program can and should be updated to reflect future changes to the project’s delivery.  

Updating programs  

Depending on the contract requirements, the accepted baseline program should be updated with actual progress at intervals of no longer than one month (or more frequently on complex projects). The program operative should input the actual progress on a copy of the accepted program to create the periodically updated or “status” program by adding additional activities (“fragnets”) and updating the activity logic and durations to create a “live”, as-built program. The more often the program is updated, the easier this process will be.  

 Any delays to the planned works should also be incorporated into the updated program, including methodology changes and EOT events. Further program revisions should be created to assess potential (“what-if”) scenarios and their potential time impact analysed.  

The updates should be saved electronically and archived. Each revision of the updated program should be accompanied by a BOS (basis of schedule) report that details any changes to the program since the previous update (the accepted program). The purpose of saving periodic updates of the program is to provide good contemporaneous evidence of what happened on the project in case of a dispute.  

The contractor must seek approval from the Superintendent or employer’s representative with every update to the baseline program. Upon approval, the updated program will become the new contractor’s program. The Superintendents view on progress should be reflected in the updated programs and disagreement resolved through the contract dispute resolution procedures.  

 “the CA’s view on progress should be reflected in the Updated Programs. The contractor’s position on the areas of disagreement should be recorded and submitted with the Updated Programs.”[1]  

The as-built method of status updating has many advantages. As well as serving as the best method of delay analysis, it gives a clear presentation of planned against actual performance (a factual account of what happened, when and why).

  

Supporting contemporaneous records and “actualising” programs  

It is systemic in construction project management that the program is only used to communicate “progress”, not the essential forecasting tool that it is supposed to be. This is primarily due to the way in which the program is updated. This may be in part to a lack of time or skillset. Typically, a perceived level of progress is determined by the program operative who is often divorced from the project. The operative may receive “status” information from the project team in relation to their perceived level of task completeness. However, more often than not, this perception is not reinforced with factual support and is incorrect.  

 The status of the works should be reinforced with evidence of progress, such as:  

  • Photographs;  

  • Measured quantities correlating with progress claims;  

  • Marked up drawings;  

  • Drawing issue registers;  

  • Material delivery dockets.  

The program operative should maintain an as-built program to maintain a historical critical path. “Actualising” activity start and finish dates or simply entering when the activity started and/or finished essentially removes historical logic, thus rendering the program useless in determining the historical critical path through the project. Similarly, relying on the software to determine the completion of an activity based on an interim perceived level of completeness often produces inaccurate forecasts.  

Delay Allowances & Contingency  

A delay allowance should not be confused with “float” or contingency. A delay allowance represents a genuine assessment of potential delays and their probable impact to the progress of the works, whereas contingency constitutes a future event or circumstance which is possible but cannot be predicted with certainty.  

Delay Allowances  

Typical delay allowance considerations might include (contract dependent):  

  • Inclement weather;  

  • Site IR disruption;  

  • Latent conditions (defined Contractor risk events);  

  • Resource availability and productivity;  

  • Changes to construction methodology or complexity not identified at contract award.  

 AS4300-1995 (un-amended) allows for an extension of time to be claimed for inclement weather. However, most standard forms are amended to the effect that a inclement weather delay allowance should be pre-determined and incorporated into the date for PC.  

  

Typical Clause 35.5 (amended)  

(a) The Contractor acknowledges that the Approved Program allows for anticipated delays to the performance of the Works by reason of:  

(i) Inclement Weather and the effects of Inclement Weather;  

(ii) Weekends, public holidays, rostered days off and other foreseeable breaks in the continuity of the Works; and  

(iii) Subject to clause 35.5(d), any other delays that is reasonable having regard to the nature of the Works.  

The contractor is not entitled to any extension of time for Practical Completion of the Works if any delays to the progress of the Works for any of the anticipated delays noted in this clause 35.5(a), all of which are and will remain at the contractor’s risk.  

Contingency  

Recovery plans and strategies should be developed early on for high-risk activities to mitigate potential delays should they arise.  

Such contingency strategies examples include:  

  • Using air freight, not sea for long-lead-time materials from overseas  

  • Working double shift work patterns  

  • Working out of regular hours  

  • Re-sequencing of works to overlap work fronts  

  [1] SCL Delay and Disruption Protocol 2nd Edition: February 2017  

 

At Accura Consulting, our team of experts work with clients to create a tailored solution to problems. If you have an issue and want expert support, get in touch.

 
 

Related News and
Insights from Accura

Paul McArd

Paul is the founder and Managing Director of Accura Consulting. Paul has performed as an independent quantum and quantity surveying expert with over 30 appointments in high-value disputes before courts, tribunals, and in arbitration across Australia and internationally.

Previous
Previous

Key Issues Faced by Hospital Construction Projects

Next
Next

The Pros and Cons of Time Impact Analysis - a Delay Expert Guide