Andrew McKenna is an experienced construction delay expert and leads Accura Consulting’s delay and planning team, working on Queensland construction disputes from Brisbane.

Construction Delay Expert in Brisbane

Andrew spent years as a site engineer, site manager and planning manager before becoming an expert, so his delay analysis starts from how the job was actually built.

Queensland experience

Andrew has been engaged as a delay expert on a renewable energy joint venture dispute in Queensland, and on arbitrations involving renewable energy, solar farm and tunnelling projects. His wider experience covers 17 expert engagements across Australia, New Zealand, Southeast Asia, the Middle East and the UK, with project delivery experience on major rail, road and pipeline works.

Construction Delay in Brisbane

Queensland courts, tribunals and laws

Andrew prepares delay evidence for disputes heard in:

  • Supreme Court of Queensland, including matters sent to court-appointed referees

  • QCAT, for building disputes

  • Adjudication under the Building Industry Fair Payments Act 2017 (Qld), where delay arguments must be made clearly on the papers within days

  • Arbitration and expert determination under the dispute clauses of energy, resources and infrastructure contracts

Each forum asks for something different, and Andrew shapes the analysis to fit the forum from the start.

What QLD courts have said about delay

Santos v Fluor [2025] QSC 184

Justice Freeburn considered competing delay analyses after court-appointed referees found that contract breaches caused critical delay. The defendant argued a strict “but-for” comparison was required. The court disagreed, accepting that delay can be proved through reasoned analysis backed by contemporaneous project data, and that the SCL Delay and Disruption Protocol is a benchmark, not a rulebook. Andrew's view: courts want a method that suits the records and is explained plainly, not the most theoretical model.

Read Andrew's analysis.

The lesson for Queensland claims

On large, interdependent projects, the strength of a delay case comes from contemporaneous records and a clearly explained method. If the referees or the court can follow the reasoning, it will be hard to overturn.

Frequently Asked Questions

Insights


Featured Insights